The Operation Process

1.
Meeting and declaration of the cargo between Stevedore, Agent, Surveyior, Insurance, with Caption and Chief Officer.

2.
Preparation of gang way and stevedoring labors going to onboard

3.
Give safety briefing to worker and tarpaulin installation

4.
Preparation of equipments

5.
Seal inspection and open hatch cover.

6.
Machinery standby at warehouse

7.
Wharf equipment handler

8.
Discharging start.

9.
Preparation of delivery order (DO)

10.
Lorry carried the cargo from vessel to warehouse / factory.

11.
Placing machinery onboard

12.
Sweeping of the cargo at whart area

13.
Sweeping of the cargo on deck.

14.
Machinery heaping the cargo in the warehouse.

15.
Consigne site visit during operation

16.
Maintenance and foundy area own by us in Prai Bulk Cargo Terminal. We are open 24 hours including public holiday. (Emergency onboard to repair)

17.
Mantainence/others

18.
Foundry Repair/others